AIP Supplement for Thailand

AIRAC AIP SUP

B 21/26

Effective from 01 OCT 2026

to 14 DEC 2026

Published on 20 AUG 2026

  THE CONSTRUCTION OF RUNWAY END SAFETY AREA (RESA) RUNWAY 03 AND RUNWAY 21
AT KHON KAEN AIRPORT (VTUK)

1  INTRODUCTION

With effect from 1 October 2026 at 1500 UTC until 14 December 2026 at 2200 UTC, the purpose of this AIRAC AIP Supplement is to inform all concerned regarding the construction of Runway End Safety Area (RESA) of Runway 03 and Runway 21 at Khon Kaen Airport.

2  CONSTRUCTION AREA

The construction area will be conducted at the end of Runway 03 and Runway 21.

3  WORKS SCHEDULE AND CONSTRUCTION PHASES

3.1 The construction work will be on a daily basis during 1500 – 2200 UTC. However, it will be started after the last flight operation with prior permission from air traffic control unit.
3.2 The works schedule consisting of construction of Runway End Safety Area (RESA), for 2 phases will be as following:
PhasePeriodKey ActivitiesTime (UTC)
Phase 11 Oct 2026 - 31 Oct 2026The Construction of
RESA RWY 03
(Dimension: 90 x 90 m)
1500 - 2200
Phase 21 Nov 2026 - 14 Dec 2026The Construction of
RESA RWY 21
(Dimension: 240 x 90 m)
1500 - 2200

4  PRECAUTIONS

4.1 All construction equipment will be kept clear during aircraft arrival and departure operations.
4.2 All aircraft operators operating during these periods will be advised caution during take-off and landing by air traffic control unit.

5  AVAILABILITY OF VISUAL AIDS

5.1 Visual aids, markings and lightings for the movement area will be available.
5.2 The taxiway lighting system will be serviceable for aircraft operations.
5.3 The runway lighting system and PAPI for RWY 03/21 will remain serviceable.

6  OTHERS

6.1 The construction area will be blocked off by 0.55 metres-high frangible barricades painted in an alternate band of red and white. The barricades will be lighted by omni-directional fixed red lights at night and during limited visibility condition.
6.2 The layouts of construction areas are shown in attachment.

7  CONTACTS

For further information contact via the following:

7.1 Mrs. Wasanan Srilek
Tel: +669 9497 1628
E-mail: [email protected]
7.2 Mr. Badin Buttayotee
Tel: +669 0909 0381
E-mail: [email protected]

8  VALIDITY

This AIRAC AIP Supplement will remain current until 14 December 2026 at 2200 UTC. Any changes to this AIP Supplement will be notified through NOTAM.