AIP Supplement for Thailand

AIRAC AIP SUP

B 11/25

Effective from 12 JUN 2025

to 31 OCT 2025

Published on 01 MAY 2025

  OPENING OF NEW APRON AND TAXIWAY A AND B, EXTENSION OF RUNWAY, TAXIWAY AND APRON,
CONSTRUCTION OF NEW ARFF STATION AND REVISION OF AIRFIELD LIGHTING SYSTEMS
AT BURI RAM AIRPORT (VTUO)

1  INTRODUCTION

With effect from 12 June 2025 at 1301 UTC to 31 October 2025 at 0000 UTC, this AIRAC AIP Supplement is to inform all concerned of construction works such as runway and taxiway extension, apron expansion, construction of a new ARFF Station and revision of airfield lighting systems revision and the opening of apron and taxiway (A and B) at Buri Ram Airport. The details are as follows:

2  OPENING OF NEW APRON AND TAXIWAY B

Apron (Aircraft Stand No. 1 - 9) and Taxiway (A and B) will be available for operational use.

3  CONSTRUCTION AND CLOSURE DETAILS

3.1 The construction works details and works performed as indicated below:
AreaDetailsPeriodTime (UTC)Remarks
Runway 04/22

Closure of Runway 04/22 revision of runway lighting systems

12 June 25 -31 Oct 251301 - 0000

except when flights
are operated

ARFF Station

Construction of new ARFF Terminal

H24-
3.2  Mobile cranes will be operated daily at a New ARFF station construction area at an angle of 60 degree and a lifting height of 25 metres as details below:
Transitional Surface
Location

Distance from
Runway Centreline
(m)

Safety Height

(m)

Remarks

15º13’39.670"N 103º15’14.782"E -

15º13’43.100"N 103º15’17.262"E -

15º13’42.348"N 103º15’18.364"E -

15º13’38.921"N 103º15’15.883"E

1905.72See Appendix B
3.3 Throughout the construction, vehicles and machinery in the site are all marked by orange and white checkered flags 90 – by – 90 - centimeters.
3.4 All personnel and vehicles require permission to enter and exit the designated areas.
3.5 All construction equipment will be kept clear before aircraft arrival and departure operation.
3.6 The chart related to the construction is attached in herewith.

4  AVAILABILITY OF VISUAL AIDS

Navigation aids will be operated as indicated below:

Navigation AidsAvailability
1. Visual aids, markings and lightingsServiceable
2. PAPI and runway lighting systems at runway 04/22
3. Runway threshold identification lights (RTIL) at runway 22
4. Simple approach lighting system (SALS) at runway 04Unserviceable

5  TRAFFIC REGULATION

5.1 All training flights are not allowed to operate at Buri Ram Airport throughout the construction period.
5.2 Pilots are required to follow instructions of Air Traffic Controller (ATC).

6  CONTACTS

6.1 Mr. Chanchai Thawma

Tel.: +668 3792 5550

E-mail: [email protected]

6.2 Mr. Patomphop Wongtala

Tel.: +666 4539 1947

E-mail: [email protected]

7  VALIDITY

This AIRAC AIP Supplement will remain current until 31 October 2025 at 0000 UTC. Any changes or postponement to this AIRAC AIP Supplement will be notified through NOTAM.