AIP Supplement for Thailand

AIRAC AIP SUP

B 18/24

Effective from 31 OCT 2024

to 31 MAR 2025

Published on 19 SEP 2024

  OPENING OF NEW APRON AND TAXIWAY A AND B, EXTENSION OF RUNWAY, TAXIWAY AND APRON,
CONSTRUCTION OF NEW ARFF STATION AND REVISION OF AIRFIELD LIGHTING SYSTEMS
AT BURIRAM AIRPORT (VTUO)

1  INTRODUCTION

This section supplements the following portion(s) of the AIP: AD

1  With effect from 31 October 2024 at 1301 UTC to 30 April 2025 at 0000 UTC, this AIRAC AIP Supplement is to inform all concerned of construction works such as runway and taxiway extension, apron expansion, construction of a new ARFF Station and revision of airfield lighting systems revision and the opening of apron and taxiway (A and B) at Buri Rum Airport. The details are as follows:

2  OPENING OF NEW APRON AND TAXIWAY A AND B

2  Apron (Aircraft Stand No 1 - 9) and Taxiway (A and B) will be available for operational use. From 31 October 2024 at 1301 UTC to 30 April 2025 at 0000 UTC.

3  DETAILS OF CONSTRUCTION AND CLOSURE PERIOD

3.1  The construction works details and works performed as indicated below:

AreaDetailsPeriodTime (UTC)Remarks
Runway 04/22

Closure of Runway 04/22 revision of runway lighting systems

31 Oct 24 -
30 Apr 25

1301 - 0000

except when flights
are operated

ARFF Station

Construction of new ARFF Station

H24-

3.2   Mobile cranes will be operated daily at a New ARFF station construction area at an angle of 60 degree and a lifting height of 25 metres as details below:

Transitional Surface
Location

Distance from
Runway Centreline
(m)

Safety Height

(m)

Remarks

15º13’39.670"N 103º15’14.782"E -

15º13’43.100"N 103º15’17.262"E -

15º13’42.348"N 103º15’18.364"E -

15º13’38.921"N 103º15’15.883"E

1905.72-

3.3  Throughout the construction, vehicles and machinery in the site are all marked by orange and white checkered flags 90 x 90 centimetres.

3.4  All personnel and vehicles require permission to enter and exit the designated areas.

3.5  All construction equipment will be kept clear before aircraft arrival and departure operation.

3.6  The chart related to the construction is attached in herewith.

4  AVAILABILITY OF VISUAL AIDS

4   Navigation aids will be operated as indicated below:

Navigation AidsAvailability
1. Visual aids, markings and lightingsServiceable
2. PAPI and runway lighting systems at runway 04/22
3. Runway threshold identification lights (RTIL) at runway 22
4. Simple approach lighting system (SALS) at runway 04Unserviceable

5  TRAFFIC LIMITATION

5.1  All training flights are not allowed to operate at Buriram Airport throughout the construction period.

5.2  Pilots are required to follow instructions of air traffic controller (ATC).

6  CONTACTS

6.1  Mr. Chakphet Thinrat

Tel: +668 1873 3109

E-mail: [email protected]

6.2  Mr. Patomphop Wongtala

Tel: +666 4539 1947

E-mail: [email protected]

7  VALIDITY

7  This AIRAC AIP Supplement will remain current until 30 April 2025 at 0000 UTC. Any changes to this AIRAC AIP Supplement will be notified through NOTAM.