This section supplements the following portion(s) of the AIP: AD
1 With effect from 23 November 2023 at 0100 UTC to 30 July 2024 at 1000 UTC, this AIP Supplement is to inform all concerned of the construction of hydrant system for aircraft fueling station at Krabi Airport.
2.1 Construction of Section Valve Chamber (SVC)
2.1.1 The construction areas are located in the following locations:
SVC1: Apron edge area (Aircraft Stand No. 20)
SVC2: Apron area (Aircraft Stand No. 10 and 11)
SVC3: Apron edge area (Aircraft Stand No. 1)
2.1.2 The construction period is from 23 November 2023 to 13 February 2024 between 0100 - 1000 UTC.
2.1.3 The Aircraft Stand No. 10 and 11 will be unserviceable during the construction period.
2.1.4 The construction area layout is shown below.
2.2 Construction and Installation of Hydrant Pit Valve
2.2.1 The construction area is located at the apron area (Aircraft Stand No. 1 - 20) and the affected aircraft stands will be unserviceable.
2.2.2 The construction period is from 9 December 2023 to 28 May 2024 between 0100 - 1000 UTC.
2.2.3 The construction will be carried out according to the work schedule as follows:
Item | Period | Area of Activities | Time (UTC) | Remarks |
---|---|---|---|---|
1 | 9 Dec 23 - 7 Jan 24 | Aircraft Stand No. 1 - 4 | 0100 - 1000 UTC | See APPENDIX Unserviceable aircraft stands |
2 | 8 Jan 24 - 6 Feb 24 | Aircraft Stand No. 17 - 20 | ||
3 | 7 Feb 24 - 2 Mar 24 | Aircraft Stand No. 10 - 12 | ||
4 | 3 - 16 Mar 24 | Aircraft Stand No. 9 | ||
5 | 17 - 30 Mar 24 | Aircraft Stand No. 8 | ||
6 | 31 Mar 24 - 13 Apr 24 | Aircraft Stand No. 7 | ||
7 | 14 - 28 Apr 24 | Aircraft Stand No. 5 - 6 | ||
8 | 29 Apr 24 - 28 May 24 | Aircraft Stand No. 13 - 16 |
2.3 Installation of Emergency Fuel Shut Off (EFSO) System
2.3.1 The installation area is located at the service road area adjacent to the apron.
2.3.2 The installation period is from 29 January 2024 to 16 May 2024 between 0100 - 1000 UTC.
2.3.3 The installation area layout is shown below.
2.4 System Testing
2.4.1 System testing will be conducted daily from 30 May 2024 to 30 July 2024 between 0100 - 1000 UTC.
2.4.2 The fuel supply system in the apron area will be tested during nighttime when no scheduled flights are operated.
2.5 The construction areas will be blocked off by barriers painted in alternate bands of red and white or orange and white and will be provided with omnidirectional fixed red lights and orange and white checkered flags.
2.6 Vehicles and machinery operating in the airside will be equipped with 90 x 90 cm orange and white checkered flags or flashing lights. Personnel in the worksites are required to wear a reflective safety vest and a safety helmet.
2.7 All personnel and vehicles require permission to enter and exit the designated areas.
2.8 Pilots are required to follow instructions of air traffic controller (ATC) throughout the construction period.
3 For further information, please refer to the following contacts.
3.1 Mr.Chanyut Srikaw
Tel: +668 0520 1455
E-mail: srikaewchanyut@gmail.com
3.2 Mr.Boonyong Jeawkok
Tel: +666 1716 4465
E-mail: blink1.618@gmail.com
3.3 Mr.Thitawat Chittchang
Tel: +668 9645 6024
E-mail: ch.thitawat@gmail.com
3.4 Ms.Wimonwan Somwang
Tel +668 6351 5482
E-mail: wimonwansomwang@gmail.com
4 This AIP Supplement will remain current until 30 July 2024 at 1100 UTC. Any changes to this AIP Supplement will be notified through NOTAM.