ContactThe Civil Aviation Authority of Thailand Tel: +662 568 8831 Fax: +662 576 1903 AFS: VTBAYOYX E-mail: [email protected] E-mail: [email protected] | AIP Supplement for Thailand![]() | AIP SUP A 21/23 Effective from 06 JUN 2023 to 08 OCT 2023 Published on 01 JUN 2023 |
This section supplements the following portion(s) of the AIP: AD
1.1 Suvarnabhumi International Airport is undergoing the taxiway and taxilane pavement reconstruction project which will commence in
June 2023. The overall project will continue for approximately 14 months and will be divided into 3 phases with 11 construction areas.
1.2 This AIP Supplement is to inform all concerned of the construction Phase 1 which expected to take 4 months, consists of 3 construction areas. The works will take place from 6 June 2023 at 01.00 UTC to 8 October 2023 at 09.00 UTC. The details of the schedule and extent of the work areas are shown in the table below. (See attachment A1-A4)
2 The details are as follows:
ConstructionArea | Closure Area | Period | Chart |
---|---|---|---|
1 |
- Taxilane T6 behind aircraft stands: B2, B4, B6 - Aircraft parking at aircraft stands: C7, C9 and 203 |
From 6 June 2023, 0100 UTC To 19 August 2023, 0900 UTC *** Remarks *** | Attachment A2 |
2 |
- Taxilane T16 |
From 14 June 2023, 0200 UTC To 27 August 2023, 0900 UTC *** Remarks *** | Attachment A3 |
3 |
- Taxiway B between Taxiway C3 and Taxiway C5, Taxiway B2 and Taxiway C4 Remark: There is a presence of machinery |
From 30 June 2023, 2300 UTC To 8 October 2023, 0900 UTC *** Remarks *** | Attachment A4 |
3.1 The construction areas will be blocked off by maximum 0.45 metres of frangible barricades painted in alternate bands of orange and white and will be lighted by omnidirectional fixed red lights along the sections of the closure areas.
3.2 The closure markings are displayed on the entrances of the closure area (yellow crosses).
3.3 Taxiways and Taxilane Centre Line Lights and the signage on the construction areas are unserviceable.
4.1 The closure period of works described in item 2 are tentative. Any revised to the closure program will be promulgated by NOTAM.
4.2 The project detail of constructions phase 2 and 3 will be issued by further AIP Supplement (s).
5 For further information contact via the following:
5.1 Unit: Aeronautical Information Services Sub-Division of Suvarnabhumi International Airport
Tel: +662 132 6931-4
Mobile: +666 2598 0608
E-mail: [email protected]
5.2 Unit: Apron Management Sub-Division of Suvarnabhumi International Airport
Tel.: +662 132 4110-2
E-mail: [email protected]
5.3 Unit: Airfield Department of Suvarnabhumi International Airport
Tel.: +662 132 8105
6 This AIP Supplement will remain current until 8 October 2023 0900 UTC. Any changes or postponement of the program of this AIP Supplement will be notified through NOTAM.