AIP Supplement for Thailand

AIP SUP

A 21/23

Effective from 06 JUN 2023

to 08 OCT 2023

Published on 01 JUN 2023

  THE CLOSURE OF TAXIWAY AND TAXILANE FOR PAVEMENT RECONSTRUCTION PHASE 1
AT SUVARNABHUMI INTERNATIONAL AIRPORT (VTBS)

1  INTRODUCTION

This section supplements the following portion(s) of the AIP: AD

1.1  Suvarnabhumi International Airport is undergoing the taxiway and taxilane pavement reconstruction project which will commence in
June 2023. The overall project will continue for approximately 14 months and will be divided into 3 phases with 11 construction areas.

1.2  This AIP Supplement is to inform all concerned of the construction Phase 1 which expected to take 4 months, consists of 3 construction areas. The works will take place from 6 June 2023 at 01.00 UTC to 8 October 2023 at 09.00 UTC. The details of the schedule and extent of the work areas are shown in the table below. (See attachment A1-A4)

2  THE TEMPORARY CLOSURE AREAS AND PERIODS

2  The details are as follows:

ConstructionAreaClosure AreaPeriodChart
1

- Taxilane T6 behind aircraft stands: B2, B4, B6
- Taxilane T7 behind aircraft stands: C1, C3, C5, 201, 202

Remarks:
- Aircraft parking stand: B2, B4, B6, C1, C3, C5, 201
and 202 are not available.

- Aircraft parking at aircraft stands: C7, C9 and 203
shall be pushed back following ATC instructions strictly
and wingwalkers shall be provided.

From

6 June 2023, 0100 UTC

To

19 August 2023, 0900 UTC

*** Remarks ***
Date and Time are tentative.
Actual date and time (if any)
will be promulgated via NOTAM.

Attachment A2
2

- Taxilane T16
- Taxilane T17 behind aircraft stands: G4, G5, 501, 503, 504, 505

Remarks:
- Aircraft parking stand: G4, G5, 501, 503, 504 and 505 are not available.
- Aircraft parking at aircraft stands: F2, F4, F6, G1, G2, G3 and 502 shall be pushed back following ATC instructions strictly and wingwalkers shall be provided.

From

14 June 2023, 0200 UTC

To

27 August 2023, 0900 UTC

*** Remarks ***
Date and Time are tentative.
Actual date and time (if any)
will be promulgated via NOTAM.

Attachment A3
3

- Taxiway B between Taxiway C3 and Taxiway C5, Taxiway B2 and Taxiway C4

Remark: There is a presence of machinery
operating in this area, maximum height 4 metres, which
does not exceed the Obstacle Free Zone (OFZ).

From

30 June 2023, 2300 UTC

To

8 October 2023, 0900 UTC

*** Remarks ***
Date and Time are tentative.
Actual date and time (if any)
will be promulgated via NOTAM.

Attachment A4

3  MARKING AND LIGHTING

3.1  The construction areas will be blocked off by maximum 0.45 metres of frangible barricades painted in alternate bands of orange and white and will be lighted by omnidirectional fixed red lights along the sections of the closure areas.

3.2  The closure markings are displayed on the entrances of the closure area (yellow crosses).

3.3  Taxiways and Taxilane Centre Line Lights and the signage on the construction areas are unserviceable.

4  Others

4.1  The closure period of works described in item 2 are tentative. Any revised to the closure program will be promulgated by NOTAM.

4.2  The project detail of constructions phase 2 and 3 will be issued by further AIP Supplement (s).

5  CONTACT

5  For further information contact via the following:

5.1  Unit: Aeronautical Information Services Sub-Division of Suvarnabhumi International Airport
Tel: +662 132 6931-4
Mobile: +666 2598 0608
E-mail: ais_vtbs@airportthai.co.th

5.2  Unit: Apron Management Sub-Division of Suvarnabhumi International Airport
Tel.: +662 132 4110-2
E-mail: apron.vtbs@airportthai.co.th

5.3  Unit: Airfield Department of Suvarnabhumi International Airport
Tel.: +662 132 8105

6  VALIDITY

6  This AIP Supplement will remain current until 8 October 2023 0900 UTC. Any changes or postponement of the program of this AIP Supplement will be notified through NOTAM.