This section supplements the following portion(s) of the AIP: AD
1 With effect from 25 November 2022 at 0100 UTC until 30 April 2023 at 1700 UTC, the purpose of this AIP Supplement is to inform all concerned regarding the construction of Runway End Safety Area (RESA) of Runway 08 and Runway 26, the construction of blast pad and service road at Hat Yai International Airport.
2 The construction area will be conducted at the end of Runway 08 and Runway 26.
3.1 The construction work will be on a daily basis during 1500 – 2300 UTC. However, it will be started after the last flight operation with prior permission from air traffic control unit.
3.2 The works schedule consisting of construction of Runway End Safety Area (RESA), Blast Pad and Service Road for 2 phases will be as following:
Phase | Period | Key Activities | Time (UTC) |
---|---|---|---|
Phase 1(See Attachment 2) | 25 NOV 2022 – 31 DEC 2022 | The Construction of RESA RWY 26 | 1500 - 2300 |
The construction of Blast Pad RWY 08 | |||
The construction of Service Road RWY 08 | |||
Phase 2(See Attachment 3) | 1 JAN 2023 – 30 APR 2023 | The Construction of RESA RWY 08 | 1500 - 2300 |
The construction of Blast Pad RWY 26 | |||
The construction of Service Road RWY 26 |
4.1 Stopway for Runway 08/26 and stopway lightings will be unserviceable during Runway End Safety Area (RESA) construction period and declared distances will be changed as following table below.
RWY Designator |
TORA (M) |
TODA (M) |
ASDA (M) |
LDA (M) | Remarks |
---|---|---|---|---|---|
1 | 2 | 3 | 4 | 5 | 6 |
Declared distances during the construction of RESA Runway 08 | |||||
08 | 3050 | 3050 | 3050 | 3050 | NIL |
26 | 3050 | 3050 | 3110 | 3050 | NIL |
Declared distances during the construction of RESA Runway 26 | |||||
08 | 3050 | 3050 | 3110 | 3050 | NIL |
26 | 3050 | 3050 | 3050 | 3050 | NIL |
4.2 The approach lighting system for RWY 08 will be unserviceable until further notice by NOTAM.
4.3 All construction equipment will be kept clear during aircraft arrival and departure operations.
4.4 All aircraft operators operating during these periods will be advised caution during take-off and landing by air traffic control unit.
4.5 In case of emergency flight, Medical-Evac flight or adhoc flight, such aircraft shall notify the ATS unit and the airport at least 30 minutes before landing.
5.1 The taxiway lighting system will be serviceable for aircraft operations.
5.2 The runway lighting system and PAPI for RWY 08/26 will remain serviceable.
6.1 The ILS will be serviceable.
6.2 The DVOR/DME will be serviceable.
7.1 The construction area will be blocked off by 0.55 metres-high frangible barricades painted in an alternate band of red and white. The barricades will be lighted by omni-directional fixed red lights at night and during limited visibility condition. (See attachment 4)
7.2 The machinery heights are not higher than 4 metres.
7.3 The layouts of construction areas are shown in attachment 1-3
8 For further information contact via the following:
Construction Company Supervisor |
Mr. Borpit Klinrussamee Tel: +668 9462 3933 Mr. Winit Wongsaman Tel: +669 3776 2772 |
VTSS Maintenance Supervisor |
Mr. Pisit Suriya Tel: +668 1542 7918 |
VTSS AIS Unit / Airside Operation Division |
Mr. Tanapat Nacajad Tel: +667 422 7510, +669 2514 5952 Email: ais.vtss@airportthai.co.th AFS: VTSSYDYX |
9 This AIP Supplement superseded NOTAM A1864/22 (C3292/22), A1997/22 (C3488/22), A1999/22 (C3491/22) and A2029/22 (C3537/22) and will remain current until 30 April 2023 at 1700 UTC. Any changes to this AIP Supplement will be notified through NOTAM.