AIP Supplement for Thailand

AIRAC AIP SUP

A 28/22

Effective from 26 JAN 2023

to 29 NOV 2023

Published on 15 DEC 2022

  THE CONSTRUCTION OF RUNWAY END SAFETY AREA (RESA) AND REINSTALLATION OF APPROACH LIGHTING SYSTEM OF RUNWAY 03/21 AT MAE FAH LUANG-CHIANG RAI INTERNATIONAL AIRPORT (VTCT)

1  INTRODUCTION

This section supplements the following portion(s) of the AIP: AD

1  With effect from 26 January 2023 at 0100 UTC to 29 November 2023 at 2259 UTC, the purpose of this AIP Supplement is to inform all concerned of the airport construction programme at Mae Fah Luang-Chiang Rai International Airport. The construction programme includes the construction of 240 m RESA and reinstallation of approach lighting system at each end of runway.

2  OPERATIONAL RESTRICTIONS

2.1   Phase 1: The construction of RESA Runway 21

2.1.1  The approach lighting system of Runway 03 (Including sequenced flashing lights) will be unserviceable.

2.1.2  Stopway and stopway lights of Runway 21 will be unavailable all phases of the construction. The declared distances for the remaining portion of RWY03/21 are as follows:

RWY DesignatorTORA (M)TODA (M)ASDA (M)LDA (M)
033000300030603000
213000300030003000

2.2  Phase 2: The construction of RESA Runway 03

2.2.1  The Localizer of Runway 03 will be unserviceable, but the glide slope of RWY 03 remains operational. The instrument approach procedures of Runway 03 will be changed to a non-precision approach.

2.2.2  The approach lighting system of Runway 21 will be unserviceable.

2.2.3  Stopway and stopway lights of Runway 03 will be unavailable. The declared distances for the remaining portion of RWY03/21 are as follows:

RWY DesignatorTORA (M)TODA (M)ASDA (M)LDA (M)
033000300030003000
213000300030003000

3  WORKS SCHEDULE AND CONSTRUCTION PHASES

3  The construction will be operated in 2 phases as follows:

PhasePeriodKey ActivitiesTime (UTC)Remark
Phase 126 JAN 2023 - 12 JUL 2023- Land levelling at THR 031501 - 2259

See Appendix A

All workers and construction equipment will be kept clear during aircraft arrival and departure operations

- Filling up an existing drainage
- Construction of a new drainage
- Construction of a blast pad at THR 03
- Construction of a service road
- Construction of a RESA Runway 21
- Uninstallation and Re-installation of
approach lighting system of Runway 03
24H
Phase 213 JUL 2023 - 29 NOV 2023- Land levelling at THR 211501 - 2259

See Appendix B

All workers and construction equipment will be kept clear during aircraft arrival and departure operations.

- Filling up an existing drainage
- Construction of a blast pad at THR 21
- Construction of a service road
- Construction of a RESA Runway 03

- Uninstallation and Re-installation of approach lighting system of Runway 21

24H

4  AVAILABILITY OF NAVIGATION AIDS

4.1  Visual Aids

4.1.1  Visual aids, markings and lightings for the movement area will be available except stopway lights will be unserviceable during construction.

4.1.2  The approach lighting system of RWY 21 will be serviceable during a construction phase 1 whilst the approach lighting system of RWY 03 is unserviceable.

4.1.3  The approach lighting system of RWY 03 will be serviceable during a construction phase 2 whilst the approach lighting system of RWY 21 is unserviceable.

4.1.4  The runway lighting system for RWY 03/21 will be serviceable.

4.2  Non- Visual Aids

4.2.1  The Glideslope of runway 03 will be serviceable.

4.2.2  The Localizer of runway 03 will be unserviceable until further notice by NOTAM.

4.2.3  The DVOR/DME will be serviceable.

4.2.4  The NDB will be serviceable.

4.3  Any changes to the availability of navigation aids will be promulgated by NOTAM.

5  PRECAUTIONS

5.1  Mae Fah Luang-Chiang Rai International Airport cannot be used as an alternate aerodrome and emergency for any flights operating during those periods.

5.2  This AIP Supplement applies the runway closure period as same as that of AIP SUP A15/22-28 JUL 2022.

6  CONTACT

6  For further information contact via the following:

Unit: Aeronautical Information Service Sub-Division, Airside Operations Division, Mae Fah Luang-Chiang Rai International Airport. (AOT)

Tel: +665 379 8162 or +665 379 8000

E-mail: ais.vtct@airportthai.co.th

7  VALIDITY

7  .This AIP Supplement will remain current until 29 November 2023 at 2259 UTC. Any changes to this AIP Supplement will be notified through NOTAM.