AIP Supplement for Thailand

AIP SUP

A 13/21

Effective from 15 AUG 2021

to 06 JUN 2023

Published on 29 JUL 2021

  REVISED THE CONSTRUCTION OF NEW TAXIWAYS AT MAE FAH LUANG-CHIANG RAI INTERNATIONAL AIRPORT

1  INTRODUCTION

This section supplements the following portion(s) of the AIP: AD

1  With effect from 15 August 2021 at 1501 UTC to 5 June 2023 at 2259 UTC, the purpose of this AIP Supplement is to inform all concerned of the airport upgrading programme at Mae Fah Luang-Chiang Rai International Airport.

The upgrading programme includes the surface maintenance of existing taxiways, apron taxilane, and the construction of a new parallel taxiway and other linking taxiways.

2  CLOSURE OF MOVEMENT AREA

2.1  Runway 03/21 will be closed due to the airport upgrading programme; daily period closure is 1501 - 2259 UTC start from 15 August 2021 to 5 June 2023. Therefore, Mae Fah Luang-Chiang Rai International Airport can not be used as an alternate aerodrome for any flights operating during those periods.

2.2  The Runway 03/21 closure program may be revised in the event of forecast or actual adverse weather conditions or other extenuating circumstances.

2.3  This AIP Supplement and relevant charts will be applicable during the whole period pertaining to the surface maintenance of existing taxiways, apron taxilane, and the construction of a new parallel taxiway and other linking taxiways.

2.4  The construction area will be blocked off by barricades painted in an alternate band of red and white, the barricades will be lighted by omni-directional fixed red lights at night and during limited visibility condition.

2.5  Any revision to the closure program will be promulgated by NOTAM.

3  PRECAUTIONS

3.1  PAPI on the right side of runway 21 will be unserviceable.

3.2  All aircraft operators operating during these periods should plan to reschedule the flight operations in accordance with slot allocation.

3.3  All aircraft operators operating during these periods shall strictly comply with the local procedures and instructions of air traffic control unit.

3.4  All construction equipment will be kept clear when runway 03/21 is operational.

3.5  Any additional/ad hoc conditions that might arise during this period are subject to the discretion of AOT.

4  WORKS SCHEDULE AND CONSTRUCTION PHASES

4  The works schedule pertains to the surface maintenance of existing taxiways, apron taxilane, and the construction of a new parallel taxiway and other linking taxiways is divided into 3 phases as following:

Phase

Period

Key Activities

Time (UTC)

Remark

Clearing Phase

15 AUG – 12 NOV 2021

- Land leveling (Establishment of the temporary landside area)

H24

See Appendix A

- Construction of a temporary service road

H24

- Withdrawal of PAPI on the right side of RWY 21

1501 - 2259

- Withdrawal of AWOS

1501 - 2259

Phase 1

13 NOV 2021 – 7 NOV 2022

- Construction of a temporary service road

H24

See Appendix B

- Construction of road to the fire station (In RWY Strip area)

1501 - 2259

- Construction of road to the fire station

H24

- Construction of a new TWY A

1501 - 2259

- Construction of a new TWY B

1501 - 2259

- Construction of a new TWY C

1501 - 2259

- Construction of a new TWY P

H24

- Construction of a new TWY D

H24

- Construction of a new TWY G

H24

- Reclamation of RWY Strip and TWY Strip

1501 - 2259

- Construction of new TWY drainage

H24

- Installation of new TWY A, B and C lighting

1501 - 2259

- Installation of new TWY P, D and G lighting

H24

- Re-installation of AWOS

1501 - 2259

- Cancellation of temporary landside area

NIL

See Appendix C

Phase 2

8 NOV 2022 – 5 JUN 2023

- Closure of TWY E for surface maintenance

H24

See Appendix C

- Closure of TWY F for surface maintenance

H24

- Construction of new TWY E

1501 - 2259

- Construction of new TWY F

1501 - 2259

- Construction of new TWY G (Cont.)

H24

- Reclamation of RWY Strip and TWY Strip

1501 - 2259

- Construction of new TWY drainage and box culvert

H24

- Installation of new TWY E and F lighting

1501 - 2259

- Installation of new TWY G lighting

H24

- Re-installation of PAPI on the right side of RWY 21

1501 - 2259

5  AVAILABILITY OF NAVIGATION AIDS

5.1  Visual Aids

5.1.1  Visual aids, markings and lightings will be available for the movement area which are opened available to aircraft operations.

5.1.2  The approach lighting system for RWY 03 will be serviceable.

5.1.3  The runway lighting system for RWY 03/21 will be serviceable.

5.1.4  PAPI on the left side of RWY 21 will be serviceable.

5.2  Non- Visual Aids

5.2.1  Approach and landing non-visual aids for RWY 03 will be available at all times during operational hours.

5.2.2  The ILS will be serviceable.

5.2.3  The DVOR/DME will be serviceable.

5.2.4  The NDB will be serviceable.

6  TRAFFIC REGULATION

6  The taxi routes for arrival in and out of the aerodrome will be advised by the air traffic control unit instructions. It is though the duty of pilot-in-command to maintain minimum clearance from the other aircraft adjacent to it on manoeuvring area.

7  CONTACT

7  For further information contact via the following:

Unit: Aeronautical Information Service Sub-Division, Airside Operations Division (AOT)

Tel: +665 379 8165 or +665 379 8000

E-mail: ais.vtct@airportthai.co.th

8  VALIDITY

8  This AIP Supplement superseded AIRAC AIP Supplement A10/21 and will remain current until 5 June 2023 at 2259 UTC. Any changes to this AIP Supplement will be notified through NOTAM.